Farmway & Ustick Roundabout Project
A construction contract in the amount of $4,322,200 has been awarded to Knife River Corporation for construction of a multi-lane roundabout at the intersection. The project includes relocation of approximately 4,000 feet of the Phyllis Canal, and replacement of the Bardsley Gulch Drain culvert under both Farmway and Ustick Roads.
Project is in final stages of preparation before paving, which is scheduled for April 6th weather permitting. After paving final work on the lighting, pedestrian beacons, signing, and striping will occur, with the project anticipated to be complete in May 2026, several weeks ahead of schedule.
Phyllis Canal Relocation- Timelapse Video Dec 2025 - March 2026
Farmway & Ustick Roundabout ProjectMiddleton & Linden Roundabout Project
Work completed to date includes installation of 2,000 feet of 18" potable water main, irrigation relocations, re-alignment of the Caldwell Highline Canal south of the intersection, construction of 200 feet of precast concrete box culvert, storm drainage piping, and about half of the roadway structural section and base materials. The large number of existing utilities within the intersection has slowed construction due to numerous conflicts. Remaining work includes final relocation of the existing pressure sewer pipeline, completing the road base, concrete work, paving, striping, and signage. In April, the construction bypass will be removed, and all four approaches to the intersection closed to allow completion of the utility connections and roadway construction. The project is expected to be complete and re-opened to the public in mid-June.
Middleton & Linden Roundabout Timelapse Video Jan 2026 - March 2026
Latest Construction Updates
All listed completion dates are tentative and subject to change
Marble Front Rd- Ward Lane to Middleton Road
For safety reasons, this section of Marble Front is permanently closed. Inadequate sight distance available at Marble Front road approach to Middelton Rd.
Pavement Rehabilitation Projects
All listed completion dates are tentative and subject to change